Meeting Date:
|
12/17/2024 - 7:00 PM
|
Category:
|
Consent Agenda A - Routine Business
|
Type:
|
Action
|
Subject:
|
(Item A-18) Resolution 2024-150 Award of Contract and Authorization to Begin Work for the Lodi High School Breezeway Repair (Interior Framing) - Project No. 0825-8425-560-21 (Mrs. Holbert)
|
:
|
|
Enclosure
|
Resolution 2024-150 Award of Contract and Authorization to Begin Work for the Lodi High School Breezeway Repair (Interior Framing) - Project No. 0825-8425-560-21
|
File Attachment:
|
|
Summary:
|
On July 16, 2024, Resolution 2024-68, the Board of Education of Lodi Unified School District authorized staff to advertise and receive bids for the work required for the Lodi High School Breezeway Repair (Interior Framing) – Project No.#0825-8425-560-21.
On December 10, 2024, six (6) bids were received. The lowest and most responsive bidder was Haggerty Construction Inc. dba Haggerty in the amount of $275,929.72, which includes a 10 percent district-controlled contingency.
Approval of this resolution certifies the Award of Contract to Haggerty Construction Inc. dba Haggerty with a bid of $275,929.72 with the total amount to be budgeted $275,929.72.
|
Funding:
|
This project will be funded with Fund 40 Special Reserves for Capital Outlay.
|
Recommendation:
|
It is recommended the Board of Education adopt Resolution 2024-150.
|
Approvals:
|
Recommended By:
|
Signed By:
|
|
Desiree Wise - Interim Facilities & Maintenance Supervisor
|
|
Signed By:
|
|
Joe Patty - Director III, Maintenance & Operations
|
|
Signed By:
|
|
Edith Holbert - Executive Director of Operations
|
|
Signed By:
|
|
Neil Young - Superintendent
|
|
|
|
|
|
|
|