|
Meeting Date:
|
|
Category:
|
Consent Agenda A - Routine Business |
|
|
Type:
|
|
Subject:
|
(Item A-24) Resolution 2024-158 Authorizing Filing of the Notice of Completion for the Outdoor Learning Shelters (8 Sites) Project No. 3213-4416-10 (Mrs. Holbert) |
|
|
:
|
|
Enclosure:
|
Reso 2024-158 NOC Outdoor Shelters (8).ADA.pdf
Final Change Order- Outdoor Shelters (8) |
|
|
File Attachment:
|
|
Summary:
|
On April 2, 2024, the Board of Education adopted Resolution 2024-36 awarding a contract to AM Stephens Construction Co., Inc. of Lodi, California in the total amount of $3,751,000.00, which included a district-controlled contingency. There was a deductive change order for this project in the amount of $156,505.00. The final contract price is $3,594,495.00.
All work associated with this project has now been completed. This action will authorize the acceptance of the contract and filing of the NOC for the Outdoor Learning Shelters (8 Sites) Project 3213-4416-10. |
|
|
Funding:
|
This project was funded by ESSER III Funding. |
|
|
Recommendation
|
It is recommended the Board of Education adopt Resolution 2024-158. |
|
|
Approvals:
|
Recommended By: |
Signed By: |
|
Desiree Wise - Interim Facilities & Maintenance Supervisor |
|
Signed By: |
|
Joe Patty - Director III, Maintenance & Operations |
|
Signed By: |
|
Edith Holbert - Executive Director of Operations |
|
Signed By: |
|
Neil Young - Superintendent |
|
|
|
|
|
|
|